This project had been started by another contractor before Mahtecsa became involved and was left partially finished due to execution problems. The client then entrusted the project to the Mahtecsa team. After assessing the existing conditions, concrete drilling, post-installed rebar, and steel plate installation were carried out carefully and in accordance with execution requirements, bringing the project to successful completion. This experience demonstrates Mahtecsa’s ability to complete challenging projects and turn unfinished work into successful final outcomes.
In this project, Mahtaksa was responsible for the complete execution of all technical and operational processes.

Initial project assessment and technical consultation to support informed decision-making and selection of the appropriate execution approach.

Execution of structural and concrete works, including foundations, structural frames, and structural components, with continuous quality control.

Management of the execution process, supervision of work progress, and schedule control to ensure the organized and efficient delivery of projects.

Execution of civil engineering and construction projects from the planning stage through final handover, in compliance with technical requirement
We execute projects through a transparent, engineering-driven process, from planning to final handover, ensuring precise control over quality, time, and cost.
1
Reviewing connection locations and assessing existing conditions before operations begin
2
Drilling concrete at the required locations for post-installed rebar
3
Installing post-installed rebar to create the structural connection
4
Installing the steel plate and completing the connection after rebar installation
During the execution of this project, the Mahtaksa team encountered a range of technical and operational challenges. Careful management of these challenges played a key role in the successful completion of the projec
During the execution of this project, the Mahtaksa team encountered a range of technical and operational challenges. Careful management of these challenges played a key role in the successful completion of the project.
Submit your request, and the technical team at Fater Sazeh Iranian will conduct an initial review of your project and contact you as soon as possible to provide consultation and further details.
Every project begins with a defined plan, but sometimes execution does not proceed according to the initial schedule and the project encounters challenges along the way. This project had been started by another contractor before Mahtecsa became involved, but the execution was not brought to completion and the project was left partially finished. Given the existing conditions, the client entrusted Mahtecsa with continuing the work and completing the remaining sections.
When Mahtecsa entered the project, part of the execution work had already been completed, including:
Because the previous work had been stopped, continuing the project required a detailed assessment of existing conditions and coordination of the new work with the completed sections.
After the Mahtecsa team arrived, the existing project conditions were assessed first.
At this stage, the following items were evaluated:
The purpose of this assessment was to ensure precise execution and prevent problems in the subsequent connection process.
First, the project’s existing conditions were assessed and the locations required for continuing operations were identified so that the next stages could be carried out in accordance with actual site conditions.
Concrete drilling was carried out at the specified locations to create a suitable base for the connection.
At this stage, accurate hole positioning and proper preparation of the work area were particularly important.
After the locations were prepared, post-installed rebar was installed to create a connection between the existing concrete and new components.
Proper rebar installation included requirements such as:
.
Next, the steel plates were positioned and installed at the designated locations.
At this stage, coordination among the following was reviewed:
to ensure that the final connection was completed in accordance with the project’s execution details.
✅ Assessment of partially finished project conditions
✅ Concrete drilling
✅ Preparation of rebar installation locations
✅ Post-installed rebar
✅ Steel plate installation
✅ Completion of structural connections
The main challenge was continuing the work after the previous contractor’s unsuccessful execution. The Mahtecsa team first assessed the existing conditions and then carefully coordinated and completed the remaining operations to move the project out of its partially finished state.
The project, which had been stopped midway before Mahtecsa became involved, resumed after the client entrusted it to the Mahtecsa team, and the required execution work was completed. This project demonstrates Mahtecsa’s ability to enter challenging projects, assess existing conditions, and bring partially completed work to a final result.
For Mahtecsa, project execution is not limited to technical operations. Understanding the problem, assessing existing conditions, and providing an appropriate solution for project completion are also essential parts of the execution process. In projects like this one, the objective is not merely concrete drilling, post-installed rebar, or steel plate installation, but rather creating a reliable execution path that brings the project to a successful final result.